Planning regulatory certification
You cannot sell without the right approvals. Know which rules apply in each market and plan lab time and failures in.
Every market sets rules before a physical product can be sold: electrical safety, radio emissions, electromagnetic compatibility, hazardous substances, battery transport, and sector rules for medical, automotive or industrial equipment. The list depends on what the product is and where it ships.
Certification is a project inside your project. Identify the applicable regimes in the concept phase, because they drive design choices such as shielding, spacing, enclosure materials and whether to use a pre-certified radio module. Book test labs early. Run informal pre-scans on early builds so the formal test is not the first time you see the result.
Assume at least one failure and plan a fix-and-retest loop. Remember that later changes, including some firmware changes to radio behaviour, can require retesting.
Try this week
- List your target markets and the approvals each requires. Ask a test lab or compliance engineer to check the list.
- Add a pre-compliance scan to your next build plan and a retest loop to the schedule.
Signs you've got it
- The compliance list existed before the architecture was frozen.
- Formal certification tests confirm what pre-scans already showed.
Resources
- guideCE marking (opens in a new tab)European Commission
- guideEquipment Authorization (opens in a new tab)Federal Communications Commission
- guideRadio Equipment Directive (RED) (opens in a new tab)European Commission
- guideBatteries: dangerous goods transport guidance (opens in a new tab)International Air Transport Association
- bookDesigning Electronics that Work (opens in a new tab)Hunter Scott