Communicating schedule risk honestly
Hardware dates slip in large steps. Report risk early, in ranges and with triggers, before the slip is a fact.
Hardware schedules do not slip by days. A failed validation test or a late tool adds a whole build cycle. Executives used to software dates need to hear this from you before it happens.
Report a date as a range with the conditions attached: the early date if the next build passes, the late date if it needs another spin. Name the top risks, when each will be resolved and what you are doing about them. Update the range at every gate.
A team that hides a known risk to protect a date has only delayed the news and removed everyone's options. Reward early bad news in your own team, and carry it upward yourself, plainly, with the decision you need.
Try this week
- Rewrite your next status report with a date range, the conditions for each end and your top three risks.
- Tell your manager about one risk you have been hoping would go away, with the date you will know more.
Signs you've got it
- Executives can repeat the conditions under which your date moves.
- Your team brings you bad news early, and schedule surprises at gates have become rare.
Resources
- paperPersonal Observations on the Reliability of the Shuttle (Rogers Commission Report, Appendix F) (opens in a new tab)Richard Feynman
- bookThe Challenger Launch Decision: Risky Technology, Culture, and Deviance at NASA (opens in a new tab)Diane Vaughan
- articleGetting good at delivering bad news (opens in a new tab)Pat Kua
- articleThe Cone of Uncertainty (opens in a new tab)Steve McConnell
- articleDelusions of Success: How Optimism Undermines Executives' Decisions (opens in a new tab)Dan Lovallo and Daniel Kahneman