Step 11 of 36 · Delivery
The build plan
Each build exists to answer questions. Plan its purpose, quantity, recipients and exit criteria before parts are ordered.
The build plan is your real roadmap. Each build, from the first hand-assembled prototypes to production validation, is an expensive experiment with a fixed start date. It should exist to answer named questions.
For every build, write down the purpose, the configurations, the quantity, who receives units and what must be true at the end. Count units honestly: reliability testing destroys some, certification keeps some, and firmware, test development and the factory all need their own. Teams that under-order spend the next phase arguing over three working boards.
Plan backwards from the build date: design release, part orders, fixtures, firmware that can run the tests. Firmware that is not ready for a build wastes the build.
Try this week
- Write a unit allocation table for your next build: who gets how many, for what test, and which are destroyed.
- List the firmware features the next build needs on day one and check them against the current plan.
Signs you've got it
- Each build has a written purpose and exit criteria agreed before parts are ordered.
- No team is blocked for lack of working units in the weeks after a build.
Resources
- guideProduct Realization: companion resources, templates and checklists (opens in a new tab)Anna C. Thornton
- articleDesign Validation and Test (Field Manual glossary) (opens in a new tab)Embedded Artistry
- bookPrototype to Product: A Practical Guide for Getting to Market (opens in a new tab)Alan Cohen
- guideNASA Systems Engineering Handbook: 6.1 Technical Planning (opens in a new tab)NASA