Hardware and Embedded Engineering Manager
For engineers and software managers now leading a team that ships physical products. Changes cost weeks and money, releases cannot always be rolled back, and the supply chain is part of the system.
https://techroadmap-seven.vercel.app/roadmaps/hardware-engineering-manager
7 stages · 36 steps
Foundations
0/4What changes when the product is physical: slow loops, costly changes, several disciplines and a fixed path from prototype to production.
What changes when the product is physical
Hardware punishes late learning. Iterations take weeks, changes cost money and some mistakes ship in every unit.
Try this week
- List the next three points in your project where a decision becomes expensive to reverse, with dates.
- Ask each discipline lead what the last late change cost in weeks and in money, and write the answers down.
Resources
- Embedded System Design Issues (the Rest of the Story) (paper, Philip Koopman)https://users.ece.cmu.edu/~koopman/iccd96/iccd96.html
- The 11 deadly sins of product development (article, Alan Cohen)https://www.oreilly.com/content/the-11-deadly-sins-of-product-development/
- The Hardware Hacker: Adventures in Making and Breaking Hardware (book, Andrew "bunnie" Huang)https://nostarch.com/hardwarehackerpaperback
The disciplines and how they misread each other
Electrical, mechanical, firmware and test engineers work on different clocks and assume different things are easy to change.
Try this week
- Ask each lead to write three things they assume another discipline will handle. Compare the lists in one meeting.
- Start a one-page budget table for power, thermal, memory and cost with an owner for each line.
Resources
- A Schematic Review Checklist for Firmware Engineers (article, Mark Schulte)https://interrupt.memfault.com/blog/schematic-review-checklist
- NASA Systems Engineering Handbook: 2.0 Fundamentals of Systems Engineering (guide, NASA)https://www.nasa.gov/reference/2-0-fundamentals-of-systems-engineering/
- Making Embedded Systems, 2nd Edition (book, Elecia White)https://www.oreilly.com/library/view/making-embedded-systems/9781098151539/
- NASA Systems Engineering Handbook: 6.3 Interface Management (guide, NASA)https://www.nasa.gov/reference/6-3-interface-management/
Phases from prototype to mass production
Know what each phase is meant to prove, from first prototype to production ramp, and what must be true to leave it.
Try this week
- Write the exit criteria for your current phase on one page and ask your leads which ones are not yet met.
- Read the last gate review and list every issue that was waived. Check where each one stands today.
Resources
- Product Realization: Going from One to a Million (book, Anna C. Thornton)https://www.wiley.com/en-us/Product+Realization%3A+Going+from+One+to+a+Million-p-9781119649533
- Prototype to Product: A Practical Guide for Getting to Market (book, Alan Cohen)https://www.oreilly.com/library/view/prototype-to-product/9781449362959/
- Engineering Validation and Test (Field Manual glossary) (article, Embedded Artistry)https://embeddedartistry.com/fieldmanual-terms/engineering-validation-and-test/
- NASA Systems Engineering Handbook: 3.0 NASA Program/Project Life Cycle (guide, NASA)https://www.nasa.gov/reference/3-0-nasa-program-project-life-cycle/
- Product Design and Development (book, Karl Ulrich, Steven Eppinger and Maria Yang)https://www.mheducation.com/highered/product/product-design-and-development-7-ulrich.html
Cost of change over time
The price of a change rises in steps at each commitment. Know the steps and decide what must be right before each one.
Try this week
- Draw your project timeline and mark each commitment point with what a change costs before and after it.
- Introduce a one-page change request for anything already frozen: reason, cost, schedule effect, approver.
Resources
- NASA Systems Engineering Handbook: 2.5 Cost Effectiveness Considerations (guide, NASA)https://www.nasa.gov/reference/2-5-cost-effectiveness-considerations/
- Six Myths of Product Development (article, Stefan Thomke and Donald Reinertsen)https://hbr.org/2012/05/six-myths-of-product-development
- Best Practices: Capturing Design and Manufacturing Knowledge Early Improves Acquisition Outcomes (paper, U.S. Government Accountability Office)https://www.gao.gov/products/gao-02-701
- The Second Toyota Paradox: How Delaying Decisions Can Make Better Cars Faster (article, Allen Ward and colleagues)https://sloanreview.mit.edu/article/the-second-toyota-paradox-how-delaying-decisions-can-make-better-cars-faster/
People
0/5Hiring and growing electrical, mechanical, firmware and test engineers, running a safe lab and reviewing designs across disciplines.
Hiring across four disciplines
You will hire people whose work you cannot judge yourself. Build loops that test real skill in each discipline.
Try this week
- Add a design walkthrough to your loop: the candidate presents a shipped design and what changed after first test.
- Find one senior practitioner per discipline, inside or outside, who will join interviews for roles you cannot judge.
Resources
- The Holloway Guide to Technical Recruiting and Hiring (book, Ozzie Osman and contributors)https://www.holloway.com/g/technical-recruiting-hiring
- Running a Humane Interview Process (article, Will Larson)https://lethain.com/running-humane-interview-process/
- Making Embedded Systems, 2nd Edition (book, Elecia White)https://www.oreilly.com/library/view/making-embedded-systems/9781098151539/
- UK-SPEC: UK Standard for Professional Engineering Competence and Commitment (guide, Engineering Council)https://www.engc.org.uk/our-role-as-regulator/setting-standards/uk-spec-professional-engineering-competence-and-commitment
Lab culture and safety
A lab holds mains voltage, batteries, heat and moving parts. Safety and care for shared equipment are yours to set.
Try this week
- Walk the lab with your most experienced engineer and list every hazard, then ask who is trained for each.
- Label every prototype with revision, owner and known faults, and agree where broken units go.
Resources
- Safety in electrical testing at work (INDG354) (guide, Health and Safety Executive)https://www.hse.gov.uk/pubns/indg354.htm
- Control of Hazardous Energy (Lockout/Tagout) (guide, Occupational Safety and Health Administration)https://www.osha.gov/control-hazardous-energy
- Battery Safety (guide, University of Illinois Division of Research Safety)https://drs.illinois.edu/Page/SafetyLibrary/BatterySafety
- EOS/ESD Fundamentals (guide, EOS/ESD Association)https://www.esda.org/esd-overview/esd-fundamentals/
- What Is Psychological Safety? (article, Amy Gallo)https://hbr.org/2023/02/what-is-psychological-safety
Growing specialists
Deep experts in analog, radio, mechanics or test are rare and slow to grow. Give them a path that does not end in management.
Try this week
- List the skills only one person on your team has. For each, name who will learn it and by when.
- Write a short description of the next level for one specialist and discuss it with them.
Resources
- Staff archetypes (article, Will Larson)https://staffeng.com/guides/staff-archetypes/
- UK-SPEC: UK Standard for Professional Engineering Competence and Commitment (guide, Engineering Council)https://www.engc.org.uk/our-role-as-regulator/setting-standards/uk-spec-professional-engineering-competence-and-commitment
- NASA Systems Engineering Handbook: 2.7 Competency Model for Systems Engineers (guide, NASA)https://www.nasa.gov/reference/2-7-competency-model-for-systems-engineers/
- Roles and Competencies (SEBoK) (guide, Systems Engineering Body of Knowledge)https://sebokwiki.org/wiki/Roles_and_Competencies
Cross-discipline design reviews
A review before release is the cheapest test you will ever run. Make reviews routine, prepared and cross-discipline.
Try this week
- Schedule the next design review at least a week before the release date and send the material in advance.
- Start a review checklist from the last five problems your team found late.
Resources
- NASA Systems Engineering Handbook: Appendix N, Guidance on Technical Peer Reviews/Inspections (guide, NASA)https://www.nasa.gov/reference/appendix-n-guidance-on-technical-peer-reviews-inspections/
- NASA Systems Engineering Handbook: 6.7 Technical Assessment (guide, NASA)https://www.nasa.gov/reference/6-7-technical-assessment/
- Embedded System Lecture Notes (peer reviews, testing, safety, security) (guide, Philip Koopman)https://users.ece.cmu.edu/~koopman/lectures/index.html
- A Schematic Review Checklist for Firmware Engineers (article, Mark Schulte)https://interrupt.memfault.com/blog/schematic-review-checklist
Contractors and design partnersoptional
Outside firms can add capacity or skills you lack. Keep the requirements, the integration and the knowledge inside.
Try this week
- For each outside partner, list what you receive at the end. Check that source files and test data are on the list.
- Name one internal engineer as technical owner for each contracted work package.
Resources
- Is the Make-Buy Decision Process a Core Competence? (paper, Charles Fine and Daniel Whitney)https://dspace.mit.edu/handle/1721.1/1626
- The Factory Floor, Part 4 of 4: Picking (and Maintaining) a Partner (article, Andrew "bunnie" Huang)https://www.bunniestudios.com/blog/2013/the-factory-floor-part-4-of-4picking-and-maintaining-a-partner/
- Inspection and the limits of trust (article, Will Larson)https://lethain.com/inspection/
- Strategic Sourcing: To Make or Not To Make (article, Ravi Venkatesan)https://hbr.org/1992/11/strategic-sourcing-to-make-or-not-to-make
Delivery
0/5Requirements, builds, lead times and integration: how to plan and run work when each iteration costs weeks and money.
Requirements and traceability
Written, testable requirements tie the disciplines together. Each one should trace to a design choice and a test.
Try this week
- Pick five top-level requirements and check that each has a number, an owner and a named test.
- Ask product which requirements they would relax first, and what each is worth to the customer.
Resources
- NASA Systems Engineering Handbook: 4.2 Technical Requirements Definition (guide, NASA)https://www.nasa.gov/reference/4-2-technical-requirements-definition/
- NASA Systems Engineering Handbook: 6.2 Requirements Management (guide, NASA)https://www.nasa.gov/reference/6-2-requirements-management/
- NASA Systems Engineering Handbook: Appendix C, How to Write a Good Requirement (guide, NASA)https://www.nasa.gov/reference/appendix-c-how-to-write-a-good-requirement/
- EARS: Easy Approach to Requirements Syntax (guide, Alistair Mavin)https://alistairmavin.com/ears/
- NASA Systems Engineering Handbook: Appendix D, Requirements Verification Matrix (guide, NASA)https://www.nasa.gov/reference/appendix-d-requirements-verification-matrix/
The build plan
Each build exists to answer questions. Plan its purpose, quantity, recipients and exit criteria before parts are ordered.
Try this week
- Write a unit allocation table for your next build: who gets how many, for what test, and which are destroyed.
- List the firmware features the next build needs on day one and check them against the current plan.
Resources
- Product Realization: companion resources, templates and checklists (guide, Anna C. Thornton)https://productrealizationbook.com/
- Design Validation and Test (Field Manual glossary) (article, Embedded Artistry)https://embeddedartistry.com/fieldmanual-terms/design-validation-test/
- Prototype to Product: A Practical Guide for Getting to Market (book, Alan Cohen)https://www.oreilly.com/library/view/prototype-to-product/9781449362959/
- NASA Systems Engineering Handbook: 6.1 Technical Planning (guide, NASA)https://www.nasa.gov/reference/6-1-technical-planning/
Long-lead items and schedule risk
Parts, tools and lab slots with long lead times set your critical path. Order early at risk and manage each risk by name.
Try this week
- List the ten longest-lead items in your product with order dates. Mark those that must be ordered before validation.
- For your top three schedule risks, write the trigger date and the fallback you would switch to.
Resources
- NASA Systems Engineering Handbook: 6.4 Technical Risk Management (guide, NASA)https://www.nasa.gov/reference/6-4-technical-risk-management/
- GAO Schedule Assessment Guide: Best Practices for Project Schedules (guide, U.S. Government Accountability Office)https://www.gao.gov/products/gao-16-89g
- The Bullwhip Effect in Supply Chains (article, Hau Lee, V. Padmanabhan and Seungjin Whang)https://sloanreview.mit.edu/article/the-bullwhip-effect-in-supply-chains/
- Performing a Project Premortem (article, Gary Klein)https://hbr.org/2007/09/performing-a-project-premortem
Hardware-software integration and bring-up
The first days with new hardware decide the weeks after. Prepare firmware, tools and a plan before the boards arrive.
Try this week
- Write the bring-up order for your next board with your hardware and firmware leads, and list the equipment needed.
- Check that firmware for the next build already runs on a development kit or an earlier revision.
Resources
- NASA Systems Engineering Handbook: 5.2 Product Integration (guide, NASA)https://www.nasa.gov/reference/5-2-product-integration/
- Making Embedded Systems, 2nd Edition (book, Elecia White)https://www.oreilly.com/library/view/making-embedded-systems/9781098151539/
- Designing Electronics that Work (book, Hunter Scott)https://designingelectronics.com/
- System Integration (SEBoK) (guide, Systems Engineering Body of Knowledge)https://sebokwiki.org/wiki/System_Integration
Agile practices that do and do not transfer
Short feedback loops and visible work transfer to hardware. Sprints that each end in a shippable product do not.
Try this week
- Pick one open design question and find the cheapest experiment that answers it before the next build.
- Hold a retrospective after your next build with all disciplines and the factory contact in the room.
Resources
- Yes, Hardware Can Be Agile! (article, Nancy Van Schooenderwoert)https://www.infoq.com/articles/hardware-can-be-agile/
- Six Myths of Product Development (article, Stefan Thomke and Donald Reinertsen)https://hbr.org/2012/05/six-myths-of-product-development
- The New New Product Development Game (article, Hirotaka Takeuchi and Ikujiro Nonaka)https://hbr.org/1986/01/the-new-new-product-development-game
- Test-Driven Development for Embedded C (book, James Grenning)https://pragprog.com/titles/jgade/test-driven-development-for-embedded-c/
Quality and test
0/6Designing for test and manufacture, proving the product works and lasts, and learning from every failure in the lab and the field.
Design for test and for manufacture
A design that works on the bench is half done. It must also be buildable at volume and testable in seconds.
Try this week
- Send your current design to your manufacturer or a manufacturing engineer and ask for a written review.
- Ask your test lead which functions cannot be tested on the line today, and what the design would need.
Resources
- The Factory Floor, Part 2 of 4: On Design for Manufacturing (article, Andrew "bunnie" Huang)https://www.bunniestudios.com/blog/2013/the-factory-floor-part-2-of-4on-design-for-manufacturing/
- Manufacturability and Producibility (SEBoK) (guide, Systems Engineering Body of Knowledge)https://sebokwiki.org/wiki/Manufacturability_and_Producibility
- IEEE 1149.1-2013: Standard for Test Access Port and Boundary-Scan Architecture (guide, IEEE Standards Association)https://standards.ieee.org/ieee/1149.1/4484/
- Designing Electronics that Work (book, Hunter Scott)https://designingelectronics.com/
Verification versus validation
Verification asks whether you built it to the requirements. Validation asks whether it does the job for the user.
Try this week
- Check that every requirement has a verification method and a planned date. Flag the ones with neither.
- Put the next prototypes in front of three real users and watch them without helping.
Resources
- NASA Systems Engineering Handbook: 2.4 Distinctions between Product Verification and Product Validation (guide, NASA)https://www.nasa.gov/reference/2-4-distinctions-between-product-verification-and-product-validation/
- NASA Systems Engineering Handbook: 5.4 Product Validation (guide, NASA)https://www.nasa.gov/reference/5-4-product-validation/
- Embedded Software Risk Areas: Verification & Validation (article, Philip Koopman)https://betterembsw.blogspot.com/2010/11/embedded-software-risk-areas_17.html
- General Principles of Software Validation (guide, U.S. Food and Drug Administration)https://www.fda.gov/regulatory-information/search-fda-guidance-documents/general-principles-software-validation
Hardware-in-the-loop and automated test
Automated tests on real hardware catch regressions that host tests miss. A test rig is a product with an owner and a budget.
Try this week
- Ask how long it takes to learn that a firmware change broke a basic hardware function. Set a target.
- Name an owner for test rigs and reserve units for them in the next build allocation.
Resources
- Test-Driven Development for Embedded C (book, James Grenning)https://pragprog.com/titles/jgade/test-driven-development-for-embedded-c/
- Continuous Integration for Embedded Systems (article, Tayyar Guzel)https://www.embeddedrelated.com/showarticle/1084.php
- Test Pyramid (article, Martin Fowler)https://martinfowler.com/bliki/TestPyramid.html
- Building Better Firmware with Continuous Integration (article, François Baldassari)https://interrupt.memfault.com/blog/continuous-integration-for-firmware
Reliability and environmental testing
Products fail from heat, cold, vibration, moisture and time. Test for them on purpose and budget the units and weeks.
Try this week
- Ask for the reliability test plan and check that it states the intended product lifetime and use conditions.
- List which reliability results must be in hand before shipment, and confirm units and lab time are booked.
Resources
- Assessing Product Reliability (NIST/SEMATECH e-Handbook of Statistical Methods, chapter 8) (guide, NIST)https://www.itl.nist.gov/div898/handbook/apr/apr.htm
- IEC 60068-1:2013 Environmental testing, Part 1: General and guidance (guide, International Electrotechnical Commission)https://webstore.iec.ch/en/publication/501
- Reliability and Maintainability (guide, NASA Office of Safety and Mission Assurance)https://sma.nasa.gov/sma-disciplines/reliability-and-maintainability
- How do you plan a reliability assessment test? (NIST/SEMATECH e-Handbook, 8.3.1) (guide, NIST)https://www.itl.nist.gov/div898/handbook/apr/section3/apr31.htm
Failure analysis and root cause
Every failure is paid-for information. Keep the failed unit, find the mechanism, and fix the cause as well as the symptom.
Try this week
- Start a failure log with serial number, build, conditions, owner and status. Review open items weekly.
- Pick one closed failure and ask whether the mechanism was reproduced or only explained.
Resources
- 5 Whys (article, Lean Enterprise Institute)https://www.lean.org/lexicon-terms/5-whys/
- A3 Problem-Solving: A Resource Guide (guide, Lean Enterprise Institute)https://www.lean.org/lexicon-terms/a3-report/
- How Complex Systems Fail (paper, Richard Cook)https://how.complexsystems.fail/
- Strategies for Learning from Failure (article, Amy Edmondson)https://hbr.org/2011/04/strategies-for-learning-from-failure
Field returns
Returned units are your most honest test data. Build the loop from customer complaint to engineering before you ship.
Try this week
- Trace one returned unit back to its build, parts lots and factory test record. Note every step that was hard.
- Ask quality or legal what the reporting duty and deadline are if a safety defect is found in your markets.
Resources
- Duty to Report to CPSC: Rights and Responsibilities of Businesses (guide, U.S. Consumer Product Safety Commission)https://www.cpsc.gov/Business--Manufacturing/Recall-Guidance/Duty-to-Report-to-the-CPSC-Your-Rights-and-Responsibilities
- Recall Guidance (guide, U.S. Consumer Product Safety Commission)https://www.cpsc.gov/Business--Manufacturing/Recall-Guidance
- The "Bathtub" curve (NIST/SEMATECH e-Handbook, 8.1.2.4) (guide, NIST)https://www.itl.nist.gov/div898/handbook/apr/section1/apr124.htm
- Recalls, Corrections and Removals (Devices) (guide, U.S. Food and Drug Administration)https://www.fda.gov/medical-devices/postmarket-requirements-devices/recalls-corrections-and-removals-devices
Safety and compliance
0/5What a leader must understand about functional safety, hazard analysis, certification, device security and the evidence behind them.
Functional safety for leaders
If a malfunction of your product can hurt someone, safety becomes an engineering discipline with its own process and proof.
Try this week
- Ask what the worst credible malfunction of your product is and who could be harmed. Write the answer down.
- Find out which safety standard applies to your product category and who in the company owns it.
Resources
- IEC 61508-1:2010 Functional safety of electrical/electronic/programmable electronic safety-related systems, Part 1 (guide, International Electrotechnical Commission)https://webstore.iec.ch/en/publication/5515
- ISO 26262-1:2018 Road vehicles, Functional safety, Part 1: Vocabulary (guide, International Organization for Standardization)https://www.iso.org/standard/68383.html
- Embedded System Lecture Notes (peer reviews, testing, safety, security) (guide, Philip Koopman)https://users.ece.cmu.edu/~koopman/lectures/index.html
- Embedded Software Development for Safety-Critical Systems, Second Edition (book, Chris Hobbs)https://www.taylorfrancis.com/books/mono/10.1201/9780429323010/embedded-software-development-safety-critical-systems-second-edition-chris-hobbs
Risk and hazard analysis
Hazard analysis asks how the product can hurt people. FMEA asks how parts can fail. Lead both as living documents.
Try this week
- Hold a ninety-minute session on one subsystem: list ways it could cause harm and what stops each one.
- Open your current FMEA or risk file and compare the date of its last update with the last design change.
Resources
- ISO 14971:2019 Medical devices: Application of risk management to medical devices (guide, International Organization for Standardization)https://www.iso.org/standard/72704.html
- IEC 60812:2018 Failure modes and effects analysis (FMEA and FMECA) (guide, International Electrotechnical Commission)https://webstore.iec.ch/en/publication/26359
- STAMP Materials: STPA and CAST handbooks and tutorials (guide, MIT Partnership for Systems Approaches to Safety and Security)https://www.mit.stamp-institute.com/materials
- System Safety (MIT OpenCourseWare 16.63J) (guide, Nancy Leveson)https://ocw.mit.edu/courses/16-63j-system-safety-spring-2016/
Planning regulatory certification
You cannot sell without the right approvals. Know which rules apply in each market and plan lab time and failures in.
Try this week
- List your target markets and the approvals each requires. Ask a test lab or compliance engineer to check the list.
- Add a pre-compliance scan to your next build plan and a retest loop to the schedule.
Resources
- CE marking (guide, European Commission)https://single-market-economy.ec.europa.eu/single-market/goods/ce-marking_en
- Equipment Authorization (guide, Federal Communications Commission)https://www.fcc.gov/engineering-technology/laboratory-division/general/equipment-authorization
- Radio Equipment Directive (RED) (guide, European Commission)https://single-market-economy.ec.europa.eu/sectors/electrical-and-electronic-engineering-industries-eei/radio-equipment-directive-red_en
- Batteries: dangerous goods transport guidance (guide, International Air Transport Association)https://www.iata.org/en/programs/cargo/dangerous-goods/lithium-batteries/
- Designing Electronics that Work (book, Hunter Scott)https://designingelectronics.com/
Security for connected devices
A connected device is an attack surface in someone's home or plant for years. Security is a design input and a lasting duty.
Try this week
- Check your product against one published baseline for connected device security and list the gaps.
- Ask who would receive a vulnerability report today and how long a signed fix would take to reach devices.
Resources
- NIST IR 8259: Foundational Cybersecurity Activities for IoT Device Manufacturers (guide, NIST)https://csrc.nist.gov/pubs/ir/8259/final
- Cyber Resilience Act (guide, European Commission)https://digital-strategy.ec.europa.eu/en/policies/cyber-resilience-act
- Code of Practice for Consumer IoT Security (guide, UK Government)https://www.gov.uk/government/publications/code-of-practice-for-consumer-iot-security
- OWASP Internet of Things Project (guide, OWASP Foundation)https://owasp.org/www-project-internet-of-things/
- PSIRT Services Framework 1.1 (guide, Forum of Incident Response and Security Teams)https://www.first.org/standards/frameworks/psirts/psirt_services_framework_v1.1
Documentation and audit trail
In regulated products, what is not recorded did not happen. Make records a by-product of the work, not a project at the end.
Try this week
- Pick one built unit and try to show its exact hardware revision, parts list and firmware build.
- List the records your regulator or key customer expects and check which exist today.
Resources
- NASA Systems Engineering Handbook: 6.5 Configuration Management (guide, NASA)https://www.nasa.gov/reference/6-5-configuration-management/
- Quality Management System Regulation (QMSR) (guide, U.S. Food and Drug Administration)https://www.fda.gov/medical-devices/postmarket-requirements-devices/quality-management-system-regulation-qmsr
- IEC 62304:2006+AMD1:2015 Medical device software: Software life cycle processes (guide, International Electrotechnical Commission)https://webstore.iec.ch/en/publication/22794
- Configuration Management (SEBoK) (guide, Systems Engineering Body of Knowledge)https://sebokwiki.org/wiki/Configuration_Management
Manufacturing and field
0/6Working with a factory, keeping parts available, testing every unit, updating firmware and supporting products for years.
Working with a contract manufacturer
The factory builds what you specify, not what you meant. Treat it as a partner, visit it, and write everything down.
Try this week
- Ask your manufacturer what is unclear or missing in your documentation. Fix the top three items.
- Plan for an engineer to be on the line for the first days of your next build.
Resources
- The Factory Floor, Part 4 of 4: Picking (and Maintaining) a Partner (article, Andrew "bunnie" Huang)https://www.bunniestudios.com/blog/2013/the-factory-floor-part-4-of-4picking-and-maintaining-a-partner/
- Poorly Made in China: An Insider's Account of the China Production Game (book, Paul Midler)https://www.wiley.com/en-us/Poorly+Made+in+China%3A+An+Insider%27s+Account+of+the+China+Production+Game%2C+Revised+and+Updated+Edition-p-9780470928073
- Product Realization: Going from One to a Million (book, Anna C. Thornton)https://www.wiley.com/en-us/Product+Realization%3A+Going+from+One+to+a+Million-p-9781119649533
- The Hardware Hacker: Adventures in Making and Breaking Hardware (book, Andrew "bunnie" Huang)https://nostarch.com/hardwarehackerpaperback
The bill of materials and obsolescence
The bill of materials is the product. Control every line, know your single sources and plan for parts that disappear.
Try this week
- Review your parts list for single-sourced and long-lead components and mark which have a qualified alternative.
- Find out who receives supplier change and end-of-life notices, and what happened to the last three.
Resources
- The Factory Floor, Part 1 of 4: The Quotation (or, How to Make a BOM) (article, Andrew "bunnie" Huang)https://www.bunniestudios.com/blog/2013/the-factory-floor-part-1-of-4the-quotation-or-how-to-make-a-bom/
- IEC 62402:2019 Obsolescence management (guide, International Electrotechnical Commission)https://webstore.iec.ch/en/publication/59531
- Designing Electronics that Work (book, Hunter Scott)https://designingelectronics.com/
Production test
Every unit is tested on the line. You own the test design, its coverage, its limits and the data it produces.
Try this week
- List the functions a customer uses and mark which the production test checks. Close the largest gap.
- Ask for first-pass yield and the top three failure causes from the last build.
Resources
- Exclave: Hardware Testing in Mass Production, Made Easier (article, Andrew "bunnie" Huang)https://www.bunniestudios.com/blog/2018/exclave-hardware-testing-in-mass-production-made-easier/
- Gauge R & R studies (NIST/SEMATECH e-Handbook, 2.4) (guide, NIST)https://www.itl.nist.gov/div898/handbook/mpc/section4/mpc4.htm
- Process or Product Monitoring and Control (NIST/SEMATECH e-Handbook, chapter 6) (guide, NIST)https://www.itl.nist.gov/div898/handbook/pmc/pmc.htm
- The Factory Floor, Part 2 of 4: On Design for Manufacturing (article, Andrew "bunnie" Huang)https://www.bunniestudios.com/blog/2013/the-factory-floor-part-2-of-4on-design-for-manufacturing/
Firmware updates in the field
Field updates are your only way to fix shipped units, and a failed one can kill a device. Decide the update design early.
Try this week
- Cut power to a test unit at random points during an update, many times, and confirm it always recovers.
- List hardware revisions and firmware versions in the field and check which combinations your release tests cover.
Resources
- RFC 9019: A Firmware Update Architecture for Internet of Things (paper, Brendan Moran, Hannes Tschofenig, David Brown and Milosch Meriac)https://datatracker.ietf.org/doc/html/rfc9019
- Device Firmware Update Cookbook (article, François Baldassari)https://interrupt.memfault.com/blog/device-firmware-update-cookbook
- RFC 8240: Report from the Internet of Things Software Update (IoTSU) Workshop 2016 (paper, Hannes Tschofenig and Stephen Farrell)https://datatracker.ietf.org/doc/html/rfc8240
- SP 800-193: Platform Firmware Resiliency Guidelines (guide, NIST)https://csrc.nist.gov/pubs/sp/800/193/final
Supporting products for years
A physical product lives on after the team moves on. Decide the support period and fund the people and tools to keep it.
Try this week
- Try to rebuild the firmware of your oldest supported product from source on a clean machine.
- Write down who owns each shipped product today and how much of their time it really takes.
Resources
- NASA Systems Engineering Handbook: 3.8 Project Phase E, Operations and Sustainment (guide, NASA)https://www.nasa.gov/reference/3-8-project-phase-e-operations-and-sustainment/
- System Maintenance (SEBoK) (guide, Systems Engineering Body of Knowledge)https://sebokwiki.org/wiki/System_Maintenance
- About the Civil Infrastructure Platform (article, Civil Infrastructure Platform)https://cip-project.org/about
- Cyber Resilience Act (guide, European Commission)https://digital-strategy.ec.europa.eu/en/policies/cyber-resilience-act
Checkpoint: ready to ship in volume?checkpoint
A self-assessment before the ramp. Every no you ship with is a problem you have chosen to meet in the field.
Try this week
- Answer the six questions separately from your quality and operations leads, then compare and discuss differences.
- Turn each no into a dated item with an owner, and record who accepted the risk of shipping with it open.
Resources
- Product Realization: companion resources, templates and checklists (guide, Anna C. Thornton)https://productrealizationbook.com/
- Best Practices: DOD Can Achieve Better Outcomes by Standardizing the Way Manufacturing Risks Are Managed (paper, U.S. Government Accountability Office)https://www.gao.gov/products/gao-10-439
- NASA Systems Engineering Handbook: 5.5 Product Transition (guide, NASA)https://www.nasa.gov/reference/5-5-product-transition/
Strategy and stakeholders
0/5Make or buy, platforms, cost and margin, and honest communication with product, operations, supply chain, quality and executives.
Make versus buy for modules and platforms
Buying a module, a reference design or an operating system saves months and creates a dependency. Choose where to depend.
Try this week
- List the bought modules and software in your product. For each, note what happens if the supplier ends it.
- Pick one bought item and estimate the volume at which a custom design would pay back.
Resources
- Is the Make-Buy Decision Process a Core Competence? (paper, Charles Fine and Daniel Whitney)https://dspace.mit.edu/handle/1721.1/1626
- Strategic Sourcing: To Make or Not To Make (article, Ravi Venkatesan)https://hbr.org/1992/11/strategic-sourcing-to-make-or-not-to-make
- Choose Boring Technology (article, Dan McKinley)https://mcfunley.com/choose-boring-technology
- NASA Systems Engineering Handbook: 6.8 Decision Analysis (guide, NASA)https://www.nasa.gov/reference/6-8-decision-analysis/
Platforms and reuse across productsoptional
A shared platform cuts cost and time across a product line, and couples every product to its weakest decision.
Try this week
- Compare your last two products block by block and list what was designed twice.
- Name the owner of your most shared firmware or hardware block and ask what they lack to maintain it.
Resources
- Planning for Product Platforms (article, David Robertson and Karl Ulrich)https://sloanreview.mit.edu/article/planning-for-product-platforms/
- Creating Project Plans to Focus Product Development (article, Steven Wheelwright and Kim Clark)https://hbr.org/1992/03/creating-project-plans-to-focus-product-development
- A Framework for Software Product Line Practice, Version 5.0 (guide, Linda Northrop and Paul Clements)https://www.sei.cmu.edu/library/a-framework-for-software-product-line-practice-version-50/
- Managing in an Age of Modularity (article, Carliss Baldwin and Kim Clark)https://hbr.org/1997/09/managing-in-an-age-of-modularity
Cost and margin awareness
Every part you add is paid for on every unit, forever. Know the cost target, the margin and what each decision does to them.
Try this week
- Get the current unit cost breakdown from operations or finance and walk through it with your leads.
- Give each subsystem a cost target and add current cost against target to your regular project review.
Resources
- Control Tomorrow's Costs Through Today's Designs (article, Robin Cooper and W. Bruce Chew)https://hbr.org/1996/01/control-tomorrows-costs-through-todays-designs
- The Factory Floor, Part 1 of 4: The Quotation (or, How to Make a BOM) (article, Andrew "bunnie" Huang)https://www.bunniestudios.com/blog/2013/the-factory-floor-part-1-of-4the-quotation-or-how-to-make-a-bom/
- Product Design and Development (book, Karl Ulrich, Steven Eppinger and Maria Yang)https://www.mheducation.com/highered/product/product-design-and-development-7-ulrich.html
- Cost Estimating and Assessment Guide: Best Practices for Developing and Managing Program Costs (guide, U.S. Government Accountability Office)https://www.gao.gov/products/gao-20-195g
Product, operations, supply chain and quality
Hardware ships through other functions. Bring product, operations, supply chain and quality into decisions from the start.
Try this week
- Meet your counterparts in supply chain, operations and quality. Ask what your team does that makes their work harder.
- Check that your programme has one schedule and one risk list that all functions use.
Resources
- What Is the Right Supply Chain for Your Product? (article, Marshall Fisher)https://hbr.org/1997/03/what-is-the-right-supply-chain-for-your-product
- Lean Product and Process Development, 2nd Edition (book, Allen Ward and Durward Sobek)https://www.lean.org/store/book/lean-product-and-process-development-2nd-edition/
- Be a better partner to product management (talk, Frankie Nicoletti)https://leaddev.com/communication/be-better-partner-product-management-2
- The Goal: A Process of Ongoing Improvement, 30th Anniversary Edition (book, Eliyahu Goldratt and Jeff Cox)https://northriverpress.com/the-goal-30th-anniversary-edition/
Communicating schedule risk honestly
Hardware dates slip in large steps. Report risk early, in ranges and with triggers, before the slip is a fact.
Try this week
- Rewrite your next status report with a date range, the conditions for each end and your top three risks.
- Tell your manager about one risk you have been hoping would go away, with the date you will know more.
Resources
- Personal Observations on the Reliability of the Shuttle (Rogers Commission Report, Appendix F) (paper, Richard Feynman)https://www.nasa.gov/history/rogersrep/v2appf.htm
- The Challenger Launch Decision: Risky Technology, Culture, and Deviance at NASA (book, Diane Vaughan)https://press.uchicago.edu/ucp/books/book/chicago/C/bo22781921.html
- Getting good at delivering bad news (article, Pat Kua)https://leaddev.com/communication/getting-good-delivering-bad-news
- The Cone of Uncertainty (article, Steve McConnell)https://www.construx.com/books/the-cone-of-uncertainty/
- Delusions of Success: How Optimism Undermines Executives' Decisions (article, Dan Lovallo and Daniel Kahneman)https://hbr.org/2003/07/delusions-of-success-how-optimism-undermines-executives-decisions